MVP

How Long Does It Take to Build an MVP?

MVP timelines by complexity: simple (2-4 weeks), moderate (4-8 weeks), complex (8-12 weeks). Factors that extend timelines and how to speed up.

Soatech Team8 min read

The Honest Answer About MVP Timelines

If you're wondering how long to build an MVP, the most accurate answer is 4-8 weeks for a typical web application. But "typical" does a lot of heavy lifting in that sentence. A landing page MVP can launch in a week. A fintech app with compliance requirements can take four months.

The timeline isn't just about how much code needs to be written. It's about decisions — how quickly you define scope, how fast you give feedback, and how disciplined you are about not adding features mid-build. The development work itself is usually the most predictable part. Everything around it is where timelines balloon.

MVP Timeline by Complexity Level

Simple MVP: 2-4 Weeks

A simple MVP has a single core feature, uses standard technology, and doesn't require third-party integrations beyond basic services (auth, email, payments).

Examples:

  • A waitlist or booking tool
  • A directory or listing site
  • A simple SaaS dashboard with one workflow
  • A content platform with user accounts

What makes it simple:

  • One user type
  • One core workflow
  • Standard authentication (email + password)
  • No complex data relationships
  • Template-based design

Team: 1-2 developers

Moderate MVP: 4-8 Weeks

This is where most MVPs land. The product has 2-4 features, involves some business logic, and requires integrations with external services. There may be multiple user types.

Examples:

  • A marketplace (buyers and sellers)
  • A project management tool
  • A B2B SaaS with team accounts
  • An e-commerce store with custom features

What adds complexity:

  • Multiple user roles (admin, customer, vendor)
  • Third-party integrations (Stripe, maps, calendars)
  • Business logic (pricing calculations, matching algorithms)
  • Data relationships (orders, invoices, permissions)
  • Custom design requirements

Team: 2-3 developers + designer

Complex MVP: 8-12 Weeks

Complex MVPs involve real-time features, advanced data processing, compliance requirements, or platform-specific development (native mobile apps).

Examples:

  • A real-time collaboration tool
  • A fintech application with regulatory compliance
  • A healthtech platform with data security requirements
  • A native mobile app for iOS and Android
  • A product with AI/ML-powered features

What adds complexity:

  • Real-time data (WebSockets, live updates)
  • Regulatory compliance (HIPAA, PCI-DSS, GDPR)
  • Complex algorithms or AI integrations
  • Native mobile development
  • High security requirements
  • Advanced data processing pipelines

Team: 3-5 developers + designer + DevOps

Timeline Comparison Table

ComplexityTimelineTeam SizeBudget RangeFeatures
Simple2-4 weeks1-2 devs$5K - $15K1-2 core features
Moderate4-8 weeks2-3 devs$15K - $40K2-4 core features
Complex8-12 weeks3-5 devs$40K - $80K3-5 core features

The 7 Factors That Extend MVP Timelines

Understanding why projects take longer than expected helps you prevent delays before they happen.

1. Unclear requirements

This is the number one timeline killer. If the development team starts coding before the scope is clearly defined, they'll spend time building the wrong things, asking questions, waiting for answers, and reworking completed features.

The fix: Invest 3-5 days in a proper discovery and scoping phase before development starts. Define the exact user flow, list every screen, and agree on what "done" looks like for each feature.

2. Too many features

Every additional feature adds time — not just for development, but for design, testing, edge case handling, and integration with other features. A 5-feature MVP doesn't take 2.5x as long as a 2-feature MVP. It takes 3-4x as long because of the interconnections.

The fix: Use the MoSCoW method to ruthlessly separate must-haves from nice-to-haves.

3. Slow feedback loops

When the development team sends a build for review and waits 5 days for feedback, the project stalls. Multiply that by every feature, and a 6-week project becomes a 10-week project — not because of development time, but because of waiting time.

The fix: Commit to reviewing progress within 24 hours. Better yet, schedule a 15-minute daily standup where you can give feedback in real time.

4. Changing scope mid-development

"Can we also add..." is the most expensive sentence in software development. Every scope change mid-build requires re-planning, possibly re-architecting, and always re-testing.

The fix: Maintain a "post-launch" list. Every new idea goes there. Review it after the MVP is live and users are giving feedback.

5. Custom design instead of component libraries

A fully custom UI with unique animations, custom icons, and bespoke components can easily add 2-3 weeks to a project. For an MVP, this time is almost always better spent on functionality.

The fix: Use a design system like shadcn/ui or Material UI. Customize colors and typography. Save the custom design for version 2.

6. Complex third-party integrations

Integrating with well-documented APIs (Stripe, Google, Twilio) is predictable. Integrating with poorly documented, legacy, or niche APIs can add days or weeks of unexpected work.

The fix: Identify all integrations during the scoping phase. If an API looks risky, build a quick test integration before committing to the full timeline.

7. No existing infrastructure

If the team has to set up hosting, CI/CD, monitoring, a testing framework, and a development environment from scratch, the first week of "development" produces zero visible features.

The fix: Use an agency or team that has these pipelines pre-configured. At Soatech, we have a standard project template that includes deployment, monitoring, and testing infrastructure — so day one of development is actually development.

Need help building this?

Our team ships MVPs in weeks, not months. Let's talk about your project.

Get in Touch

How to Speed Up Your MVP Timeline

If time-to-market is critical, here are proven strategies to compress your timeline without sacrificing quality.

Parallel workstreams

While the backend developer builds the API and database, the frontend developer builds the UI with mock data. They connect the pieces in the final sprint. This can cut 2-3 weeks off a moderate MVP.

Pre-built components

Don't build what already exists. Authentication (Clerk), payments (Stripe), email (Resend), file storage (Cloudinary), and dozens of other features are available as services that integrate in hours, not weeks.

Design sprints, not design marathons

Run a 2-3 day design sprint to create wireframes and a basic design system. Don't aim for a polished Dribbble-worthy UI. Aim for a clean, usable interface that your target users can navigate without confusion.

Fixed scope, flexible timeline (or vice versa)

You can fix the scope and let the timeline adjust, or fix the timeline and cut scope. You can't fix both. If you need to launch by a specific date, be prepared to cut features to hit it. If specific features are non-negotiable, be prepared for the timeline to extend.

Experienced team

This is the single biggest accelerator. A senior developer who has built similar products before will move 3-5x faster than a junior developer encountering these problems for the first time. The cost per hour is higher, but the total project cost is often lower.

Real MVP Timeline Examples

Example 1: B2B Scheduling SaaS

Scope: Business creates availability, customers book time slots, email confirmations, basic dashboard.

PhaseDuration
Discovery and scoping3 days
Design (wireframes + basic UI)4 days
Backend development8 days
Frontend development8 days
Integration and testing3 days
Total~5 weeks

Example 2: Two-Sided Marketplace

Scope: Vendor listings, customer browsing, search and filtering, messaging, payments, reviews.

PhaseDuration
Discovery and scoping5 days
Design (wireframes + UI)7 days
Backend development15 days
Frontend development15 days
Integration and testing5 days
Total~9 weeks

Example 3: Mobile Fitness App

Scope: User profiles, workout tracking, progress charts, push notifications, social sharing.

PhaseDuration
Discovery and scoping5 days
Design (wireframes + UI)8 days
Mobile development (cross-platform)18 days
Backend/API development12 days
Testing and app store prep7 days
Total~10 weeks

The Hidden Phase: What Happens Before Day 1

Most timelines don't account for what happens before development starts — and this phase can add 1-4 weeks depending on how prepared you are.

Before development begins, you need:

  • A clear problem statement and target user definition
  • A prioritized feature list (ideally using MoSCoW)
  • Wireframes or at least rough sketches of the user flow
  • Decisions on tech stack (or trust your development partner to choose)
  • Access to any required accounts, APIs, or credentials
  • A designated decision-maker who can give feedback within 24 hours

If you show up on day one with all of this ready, development starts immediately. If these decisions happen during the project, add 1-2 weeks to your timeline.

Get a Timeline Estimate for Your MVP

Generic timelines are a starting point, but your product has unique requirements. If you want a realistic timeline based on your specific feature set and complexity level, we can help.

Ready to get a clear timeline for your MVP? Talk to our team — we'll review your feature list, assess the complexity, and give you an honest timeline estimate. Most founders get a detailed scope and timeline within a week of their first conversation. You can also use our project calculator for a quick self-service estimate.